Why Oral Changes May Not Hold Up: Documenting Variations and Site Confirmations

We agreed then, they promised by phone, or it was sent on WeChat often cannot support an adjustment to quantities or price at settlement. The problem is usually acting after a discussion without documenting what was done. This article explains proof difficulties, required variation and site-confirmation content, and practical documentation on site.

I. Four Obstacles to Oral Variations

An oral change is not necessarily invalid, but can be difficult to prove during performance and settlement. Four obstacles recur:

  • Unclear substance: Who proposed what and how much changed depends on memory, leading to competing accounts.
  • Unclear speaker authority: On-site staff, supervisors or handling officers may lack variation authority. Whether their statement binds the entity needs separate proof.
  • Unclear relationship with the contract: If written bilateral confirmation is required, a change outside that form may be challenged as ineffective.
  • Unclear price and schedule impacts: Without records, price adjustments, extensions and additional-cost allocation cannot be calculated.

Under the variation rules of the Civil Code of the People’s Republic of China, parties may amend by agreement. Form and effect depend on the terms, correspondence and case.

II. Changes to Put in Writing

  • Scope, quantities or deliverables, such as added equipment, expanded area or extra development functions.
  • Price, pricing method or settlement basis, including unit-price changes, material substitutions and additions or removals of scheduled items.
  • Delivery dates, milestone sequence or acceptance standards, including time extensions and changed stages.
  • Technical plans, material brands or workmanship standards affecting final acceptance.
  • Any exception or concession to original terms during performance, such as payment or breach-handling arrangements.

III. Contents of a Site-Confirmation or Variation Sheet

The on-site document may later become the settlement basis. Use the following structure:

1. Variation number and linked documents: Identify the contract, term, drawing or order.

2. Proposer and reason: Identify who requested it and why, such as design changes, site conditions or counterparty requirements.

3. Substance: Specify measurable, verifiable additions and reductions.

4. Price impact: State increases or decreases, or the pricing basis and subsequent confirmation arrangement.

5. Schedule impact: State whether an extension is needed and how its start and end are determined.

6. Other impacts: Identify effects on acceptance, quality warranties or later milestones.

7. Bilateral execution: Include handling-person signatures, entity seals or signatures, and dates.

Price and schedule impacts are most often omitted. Agreeing to a change without its effects leaves another negotiation for settlement.

IV. Forms of Written Documentation

  • Supplementary agreement: For substantial price or schedule changes, execute using the original contract’s signing method.
  • Variation or site-confirmation sheet: Confirm individual, limited-value changes on site that day.
  • Work-coordination form: Record one party’s proposal and the other’s reply as a complete chain.
  • Meeting minutes and execution page: Obtain the counterparty’s signature or seal on agreed changes after the meeting.
  • Email or agreed-channel confirmation: Send through the contractually agreed channel and retain the reply with your records. Assess effect under the Electronic Signature Law of the People’s Republic of China and current rules.
  • Subsequent ratification: Promptly document work or delivery already completed on oral instructions, stating the date of implementation. Assess ratification under current rules and the case.

All forms should document who proposed, who agreed and what was agreed in the same document.

V. Four Immediate On-Site Actions

1. Agree how changes are initiated: Require written proposals, identify representatives who sign and provide for emergencies.

2. Sign before or alongside performance: If the full process cannot be completed in time, issue a coordination form or minutes confirmed by both sides’ site staff.

3. Assign a register custodian: Log each variation’s number, date, substance, price effect and signing status, matching settlement items.

4. Review periodically: At milestones or monthly, review signed and unsigned changes, obtain outstanding confirmations and document reasons for refusal.

VI. Five Common Pitfalls

  • Oral site instructions without any writing.
  • Only your signature, or only the other side’s handling-person signature without entity confirmation.
  • Substance recorded but no price or schedule impact, requiring renegotiation at settlement.
  • Completed changes left unconfirmed until settlement, inviting denial for lack of approval.
  • Variation and settlement records held separately, preventing assembly of a complete chain.

The existing Legal Risk Alerts During Contract Performance gives general guidance on writing changes down. This article instead focuses on operational documents and processes. If delivery and payment arrangements also change, check them together using Linking Delivery, Acceptance and Payment: Acceptance First or Payment First? in this series.

VII. Qualifications and Disclaimer

This article provides general information about business services and does not constitute legal advice. Its points are general guidance; individual matters require review of contracts, variations, site confirmations and correspondence. Do not apply them mechanically. No outcome or timeline is promised. For a specific dispute, engage a qualified lawyer promptly for assessment. You may contact us through this website’s contact page.

Updated October 13, 2026
  • Important notice: The information on this website is for general reference only and does not constitute legal advice. Unless otherwise stated, legal information on this website is provided in the context of the laws of the People’s Republic of China. For specific issues, you should seek advice from a qualified lawyer. Contact our lawyers for professional assistance. https://legalidea.cloud
  • Our lawyers have extensive legal experience and have handled a large number of complex and difficult legal matters for our clients, helping them meet challenges head-on.

Legal service

Professional Legal Services

Special Legal Counsel

Human resources / Corporate governance / Investment and financing / Equity incentives, and other complex legal matters

Dispute Resolution

Case assessment / Pre-litigation dispute resolution / Litigation / Arbitration

General Retainer Counsel

Flexible retainer plans for enterprises at every stage of development

Corporate Compliance

Learn more, contact us